Under CDM, which phase is the Principal Designer responsible for?

Prepare for the CIOB Live Knowledge Test. Review with flashcards, multiple-choice questions, and detailed explanations. Enhance your construction industry management skills and boost your career growth!

Multiple Choice

Under CDM, which phase is the Principal Designer responsible for?

Explanation:
The main idea is that the Principal Designer’s duties focus on health and safety during the design process. Their job is to plan, manage and coordinate design work in the pre-construction phase, making sure designers identify and address risks early and that the necessary design information is prepared for those who will build and maintain the project. Once construction starts, the hands-on safety coordination shifts to the Principal Contractor, and post-construction matters fall to other parties. So the phase where the Principal Designer is primarily responsible is the pre-construction phase.

The main idea is that the Principal Designer’s duties focus on health and safety during the design process. Their job is to plan, manage and coordinate design work in the pre-construction phase, making sure designers identify and address risks early and that the necessary design information is prepared for those who will build and maintain the project. Once construction starts, the hands-on safety coordination shifts to the Principal Contractor, and post-construction matters fall to other parties. So the phase where the Principal Designer is primarily responsible is the pre-construction phase.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy