PFI is no longer permitted.

False

True

The main idea here is how public-private partnerships have evolved: PFI has been replaced for new work by PF2, so you don’t begin new projects under the PFI model anymore. In practice, that makes the statement true because government policy now uses PF2 for new schemes, while existing PFI contracts remain in place but aren’t used to start new deals.

Understanding this helps you see why the answer is correct: the move to PF2 was driven by aims to improve value for money, transparency, and risk handling, meaning new procurements don’t use PFI. There can be legacy projects that started under PFI and continue under their original terms, but those aren’t new PFI deals. In some regions outside the typical UK context, there might be different arrangements, but for current standard practice, PFI is not used for new projects.

Depends on region

Only for legacy projects

Next question

Find the option that is right for you!

All options are one-time payments.

$25.99

30 day premium pass

All the basics to get you started

  • Ad-free experience
  • View your previous attempt history
  • Mobile app access
  • In-depth explanations
  • 30 day premium pass access
👑$59.99 $171.99 usd

6 month DELUXE pass (most popular)

Everything with the 30 day premium pass FOR 6 MONTHS! & the ultimate digital PDF study guide (BONUS)

  • Everything included in the premium pass
  • $171.99 usd value for $59.99! You save $106!
  • + Access to the ultimate digital PDF study guide
  • + 6 months of premium pass access
  • + Priority support
$15.99 $24.99

Ultimate digital PDF study guide

For those that prefer a more traditional form of learning

  • Available for instant download
  • Available offline
  • Hundreds of practice multiple choice questions
  • Comprehensive content
  • Detailed explanations
Image Description
Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy